projekte9 1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Oberkasseler Straße, Düsseldorf

 

Crisis Management

Due to the insolvency of the general contractor a non-break continuation of the construction was needed.

By installation of a so called replacement-site- management and as well as new regulations between the client and the former sub-contractors the completition was guaranteed in the scheduled time.

 
   

 

 

 

 
   
 

The New Residential Building With 31 Units – Düsseldorf-Oberkassel

 

Client :

VZN Versorgungswerk der Zahnärztekammer Nordrhein-Westfalen

 

General Contractor :

Wiemer & Trachte GmbH i.L., Niederlassung Essen

 

Project managment :

E+P Engineering + Projektmanagement GbR, Nauheim

 

Architect :

Swertz Projektmanagement + Baubetreuung GmbH, Düsseldorf

 

Value :

appox. 7.000.000 EUR

 

Date of Completition :

2006